What Order Do Builders Build Homes. (First Foundation, Second Framing, Etc ....)

Thanks

R.F.D. 2011-03-28 10:43 PM

Quote:

Originally Posted by Selvi (Post 181656)
What Order Do Builders Build Homes. (First Foundation, Second Framing, Etc ....)

Thanks

dig
footings
foundation
waterproofing
frame
roof
windows
shingles
HVAC
plumbing
electrical
insulation
drywall
flooring/tile
door frames
casing/trim
paint
fixture installation i.e. cabinets, sinks, toilets, door hardware, lights fixtures, etc
finishing touches

good2know 2011-03-29 05:56 AM

one additional item is exterior finishes which by code should be done prior to insulation

(at least house wrap on the building)

Selvi 2011-04-10 01:10 AM

After What Step Does Bricking Start?

MrTT 2011-04-10 01:57 AM

after shingles, typically

Selvi 2011-04-10 09:38 AM

We Got Shingles, But Other Homes In The Area Also Finished Shingles But They Are Just Sitting There For Weeks With No Bricks On The Home

GregS 2011-04-10 01:28 PM

Not everything happens all at once in a production build.

The key word there is production.. This is an assembly line for building houses.

A trade crew will come in and do a number of houses at one time as opposed to coming back to do just one at a time.