I am pretty sure the I-beam was a second stage as the base of the post is still in the concrete just cut off flush with the floor. I took a closer look at it last night and the I-Beam and beam are tight side by side, the joists do overhang the beam a bit so they are at least partially sitting on the I-beam from both sides. I took a measurement as well and the overall span of the beam is about 20' but it does not go foundation wall to foundation wall, on one end it is sitting on a triple 2x6 which is on an interior foundation wall, the beam is also supported the same and ends there. The other end I know is not supported properly, there is a jack post for the main beam which does continue to the foundation wall but the I-beam is only supported by a 2x4 interior wall with basically 3 2x4's but only 2 are tight together. This is less than 6" away from the jack post holding the beam so should at least be sitting on the footing. I added a sketch and pictures for more info. As for the plumbing everything looks good from what i can see. Everything done with the original move of the house looks good, it is all the extras and changes that are bad. Thanks for the tip on the electrical and HVAC, I plan to have someone look at it and give it a once over before i start re-building the basement to make sure everything looks good. Once I finish the cleanup from demolition I am going to start working on the final plan and electrical design and I will keep the lighting in mind. I was planning to keep it separate from the outlets either way, just didn't know I could waive the device count in favour of total draw amount. |
#42
|
|||
|
|||
![]() Quote:
I actually work right across the street from Lowes so that would make it even better. |
#43
|
|||
|
|||
![]() Quote:
The whole thing started with changing a light fixture, the original plan was to lay down some carpet and call it a day for a few years which snowballed into this complete gut. I plan to stay here forever so it will be worth the work in the end when the kids have somewhere nice to play. Now I just need to finish demo, clean and start the repairs so I can move on to the rebuild. |
#44
|
|||
|
|||
![]()
Thought this might help as well, here is a picture of the space on the main floor above the beam.
|
#45
|
||||
|
||||
![]()
Re I-beam: Looks like the bottom of the I-beam is 6 inches wide (4 x 2x posts).
Thats big for its purpose. Also a span > 12 ft would be fine. The 2 x 6 or 2 x 4 laminated posts is not a problem actually. Fam member has a 32 ft steel beam sitting on 4 @ 2x6 posts (each end). It was a new build and I was initially concerned. Had it checked by a structural engineer and all was good. Its holding up the second storey exterior wall and of course the roof. Compared to this, you have essentially no load. For yours, I would squeeze another 2 x in that gap on the one end, just because , and thats it. The one concern, as you have mentioned, is if there are the footings under these posts. Those pads are usually 2ft x 2ft. The little cement walls are a bonus since it gives you 8 inches+ of concrete. An old trick is the use a hammer and tap the cement floor starting away from the post location and moving closer to the post. Where it is floor only it will sound very differently than when you tap over a footing. Hard to describe but a very solid thunk. If there is a footing under these posts good to go. Pretty sure code requires a beam to have minimum 3 (maybe 4) inches surface on a beam pocket. The same should apply to the floor joists. If you have say 4 inches plus sitting on the I-beam you are good. Has the wooden beam sagged at all? A piece of string is all you need to check it. If no sag, I would not reinstall a post under the wood beam unless it can be hidden in a wall based on new design. Id probably run some 4 inch screws into each joist through the side of the beam to help hold it up. Each joist should be toe-nailed in to the beam already. Last edited by good2know; 2019-02-20 at 01:16 PM. |
#46
|
|||
|
|||
![]() Quote:
Awesome thanks, I will check if it is sagging and confirm I have 3-4" sitting on the beam. On the 2x4 end I will check to make sure there is a footing and I may still replace the wall with a triple 2x6 just for ease of mind. Adding the 4" screws wont hurt either so I will do that as well while I am at it. Thanks for all your help so far. |
#47
|
||||
|
||||
![]()
My pleasure. I really like your house and see why its a keeper
|
#48
|
|||
|
|||
![]() Quote:
I would have paid about the same for a new raised ranch in a subdivision and still had to do all the finishing work anyway. When we saw this we jumped on it right away and got lucky to get it. |
#49
|
|||
|
|||
![]()
Required bearing for beams in Part 9 of the OBC is 3 1/2".
Steel beams are typically supported by steel posts or concrete/masonry walls. The connection between a built-up wood post and a steel beam is awkward. I can't recall if the requirement for a steel, concrete or masonry support is in the building code or not. Haven't designed one of those in a while, but I used to only spec steel posts.
__________________
![]() |
#50
|
|||
|
|||
![]() Quote:
|
![]() |
Bookmarks |
Thread Tools | |
Display Modes | |
|
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
ESA inspection for basement renovation | peter919191 | Ottawa | 9 | 2012-06-12 10:14 AM |
looking for a good basement renovation company | xox2011 | Ottawa | 1 | 2011-11-23 09:13 AM |
Fall and Winter Basement Renovation Recommnedations | R.F.D. | Burlington | 9 | 2011-10-13 10:55 AM |
Quick Question about Basement renovation | Mr.NewHomeOwner | Building and Construction | 4 | 2011-06-08 12:15 PM |
Basement renovation, any recommended contractors? | htsource | Burlington | 8 | 2011-02-25 03:24 PM |