Default Opinions on Braebury?

Anyone have any opinions about Braebury in Kingston? We're considering buying, and would welcome any useful comments from people who have one of their houses, or who have dealt with them.
Reply With Quote
  #2  
Old 2008-07-06, 03:11 PM
ElectricMayhem ElectricMayhem is offline
Junior Member
Regular User
 
Join Date: Jul 2008
Location: Kingston, ON
Posts: 23
Default

After a bit of searching I found three decisions by Professional Engineers Ontario against Braebury. They found that some of Braebury's designs do not conform to the Ontario Building Code, at least as they were drawn by the engineer Braebury hired. The president of Braebury is a civil engineer, so it's hard to understand how this could happen.

http://www.peo.on.ca/complaints/Gaze...inescu2008.pdf
http://www.peo.on.ca/complaints/Gazette/Remisz2008.pdf
http://www.peo.on.ca/complaints/Gazette/Sharma2008.pdf

Last edited by ElectricMayhem; 2008-07-06 at 03:46 PM.
Reply With Quote
  #3  
Old 2008-07-23, 10:13 AM
ElectricMayhem ElectricMayhem is offline
Junior Member
Regular User
 
Join Date: Jul 2008
Location: Kingston, ON
Posts: 23
Default

I'm so glad we walked away from Braebury.

Posted for posterity:

Engineers guilty of professional misconduct
Deficiencies in house plans described as 'shocking'
Posted By IAN ELLIOT WHIG-STANDARD STAFF WRITER
Posted 4 days ago


The city refused to issue permits for new Braebury Homes models after identifying deficiencies they feared made the homes structurally unsound three times in six months in 2005.

Three professional engineers hired by Braebury to do the structural review of the houses have been found guilty of professional misconduct by the provincial body that regulates professional engineers.

Professional Engineers Ontario found Remisz Consulting Engineers and engineers Wojciech Remisz, Cristian Constantinescu and Mohan Sharma, all guilty in hearings earlier this year, the outcome of which was just released by the association.

City officials laid the complaints that led to the professional investigation of the engineers.

"Remisz Consulting Engineers Ltd. ... provided structural designs and drawings that include the overstressing of structural elements beyond acceptable limits," the tribunal found in all three cases.

The findings come in relation to production models the engineers vetted for Braebury, which had deficiencies city staff describe as "shocking" and which were found to be not up to the building code by engineers who later reviewed the work.

Two of the engineers involved are vehemently defending their work, saying what the city and the engineering board describe as deficiencies were not. They insist concerns about the plans were never raised with them until they had become a matter for a disciplinary hearing.

Wojciech Remisz, who owns the firm that also does structural engineering on bridges and other large structures, said the houses were all done by Braebury's inhouse design team and his firm had been hired only to do a check of the structural work.

He blamed poor communication by the city and Braebury for the problems and said his firm was caught in the middle.

"The city never talked to me," he said in an interview from his Ottawa office.

"The city was talking to Braebury. They weren't talking to me because they were the developer, they were the ones applying for the permit and paying the fees.

"This is an insane situation. ... I was not aware they were questioning the work."

He said the firm chose not to contest the charges because of the time and expense that would have been involved and because the tribunal only reviewed documents submitted by the city.

Remisz's firm had reviewed more than 160 Braebury designs over the years, he said, and the designs in 2005 were structurally sound.

"There is no issue to the strength of those houses," said Remisz. "No issue."

Constantinescu, who has more than 30 years of experience, said the entire experience had been a frustrating one.

"What they are calling the deficiencies on the drawings, it is our opinion [they] are not deficiencies," he said, calling the entire process dysfunctional and saying there was little or no communication among the three parties involved.

"This was a deficiency of the whole system."

The third engineer involved now works in Arizona and did not attend the disciplinary hearing.

Braebury President Peter Splinter did not return repeated calls this week.

City building inspector Jeff Gurnsey identified problems with stamped engineering drawings for Braebury production homes submitted for approval between February and August of 2005. Two of the models were identified in tribunal documents as the Da Vinci and the Copenhagen models.

Most critical among the problems the city found in the engineering drawings were that they did not show supporting steel girders at points where they should have been, some posts in the basement holding up the main floors were overloaded, and an exterior masonry veneer on one of the houses was supported on a wood beam, not steel.

One had an "unusual" arrangement where a steel supporting beam in the garage was held in place by nothing more than two telescoping supports and no supporting documentation of this arrangement was provided.

Other matters included the location of trusses not being indicated -which made it impossible to calculate loading -and no indication that special brick lintels were included around windows that required them.

An engineering expert witness said in sworn testimony at one of the tribunal sessions, "there were a number of matters that did not meet the acceptable standard of engineering practice for residential buildings.

"The details were left up in the air - literally," said Terry Willing, the city's manager of building and licensing, who is Gurnsey's boss.

He said adding to the fact that the drawings were incomplete, when city staff asked for clarification or further drawings of things such as truss layouts, Remisz engineers either wouldn't speak to them or submitted further work that was illegible.

Remisz said that's because drawings that were faxed to Braebury were then faxed to the city and by then had become illegible.

"We felt we shouldn't have to ask for that level of detail in the first place," said Willing.

"We do expect, and I expect, when my staff points out to someone that there is a deficiency, I expect them to have an answer," said Willing.

"In this case, the engineer of record was reluctant to speak to us."

Some of the deficiencies seemed to be fundamental errors, not technicalities of the building code, such as sitting exterior masonry walls on wooden posts, which could have led to it collapsing.

"That's pretty basic, and that's not done,"Willing said.

"You don't have to be an engineer to know that wood shrinks and steel doesn't."

Remisz argued many of what were labelled deficiencies were architectural and not structural.

"The masonry wall -it is not a structural thing, it's an architectural thing," he said, calling it a "grey area" of responsibility between the structural engineers and the design team.

Agreed Constantinescu, "We were not supposed to assume liability for specifications that were not structural specifications."

Remisz said different plans were going back and forth between them, Braebury and the city at the time that illustrated the wall's supports and complained the entire issue related to one drawing and not the full package of drawings created by the firm.

Constantinescu said it is standard practice to design houses with the significant structural elements planned out, but many of the routine parts of the house -known in the trade as "typical details" -are left to builders, who know how to build houses to meet code.

"For small houses, it is customary not to show all the details because there are hundreds of them, and the contractor knows how to put them in according to code," he said.

Remisz and Constantinescu both argued that the structural loads had been misinterpreted based on a single drawing and that they had been given no chance to explain their work at the hearing.

"We had proof, but we weren't allowed to present it,"Remisz said.
Reply With Quote
  #4  
Old 2008-07-23, 10:14 AM
ElectricMayhem ElectricMayhem is offline
Junior Member
Regular User
 
Join Date: Jul 2008
Location: Kingston, ON
Posts: 23
Default

The engineering company argued at one point that the deficiencies in the drawings would have been noticed and rectified in the field, but Willing said construction crews do not have the authority or the expertise to make engineering changes to structures.

Remisz, though, argued that before the building code was changed in 2006, it was allowable to do a structural analysis of a buildings but leave the precise details of something such as the design of a roof truss to a secondary review.

He said it made no sense to specify a design of truss for a house that might be built two years or more down the road by a subcontractor that might use a different form of truss than what was shown in the plans.

According to the Professional Engineers' Association, which licenses engineers to practise and owns the seals they use, a seal on a drawing indicates that the plans in question are finished work and not drafts.

"Any final documents of an engineering nature such as drawings, specifications, reports, studies, etc., should be sealed," it states.

"The seal is important because it implies a commitment to the standards of the profession and signifies to the public that a particular P. Eng has accepted professional responsibility for the document."

The panel attributed the deficiencies in the plans largely to "a deficiency of knowledge in relation to the [engineer] and not of quality assurance or quality management issues within Remisz Consulting Engineers Ltd.," and ordered all three engineers to take courses and write exams on structural analysis and structural design as a condition of keeping their licenses.

Their reprimands will be a permanent part of their records and accessible to anyone seeking to hire them as engineers. The three were fined a total of $7,500.

No action was taken against Braebury, and the company did not play a role in the disciplinary hearing, nor did the city once the original complaint was filed.

Willing said the city is responsible for ensuring that all new construction is up to code.

"We take it pretty seriously, because people can spend $300,000 or more on a house and it could be the biggest investment of their lives," he said.

Remisz defended his firm's work and said it had never been allowed to make its case with a full package of drawings or to explain the work that it had done.

"We could have sat down with the city and the engineers and cleared all this up in a 20-minute meeting, but we didn't get that chance," he said.

The firm no longer has a business relationship with Braebury and Remisz said it won't do business in Kingston again.

"We have been treated so unfairly by the PEO and by Kingston that it's painful to me," he said.

"The city can go to hell."

Likewise, Constantinescu said the firm had never had complaints about any of its previous structural work for Braebury and did not know anything was wrong until they were notified that the engineers' association had begun a case against them.

"If the city was asking Braebury something about our drawings, Braebury should call us up and get clarification," he said.

"We did not get any significant questions from Braebury, so we did not think there was anything wrong with these houses."
Article ID# 1121250
Reply With Quote
  #5  
Old 2008-11-23, 10:09 PM
urbanthink urbanthink is offline
Junior Member
 
Join Date: Nov 2008
Location: Toronto
Posts: 3
Default

well before anything else its good that you get opinions first before investing your money
Reply With Quote
  #6  
Old 2009-02-23, 10:20 PM
CoolHand CoolHand is offline
Junior Member
 
Join Date: Feb 2009
Location: Ontario
Posts: 4
Default

Braebury homes builds a good home for an affordable price. I believe the structure issues mentioned above were in Ottawa only on one select model.

Of all the big builders in Kingston Braebury is one of the better ones.

Cheers,

CH...
__________________
Cheers,

Ch...
---------------------
Review your builder today!
Reply With Quote
  #7  
Old 2010-10-10, 02:15 AM
vegetablevn vegetablevn is offline
Junior Member
 
Join Date: Oct 2010
Posts: 1
Default

Hi,

Thanks very much for this comment. It help me to think about my ideals.

If you want to do more info, you also visit at:Building inspector interview questions
Tks again and pls keep posting.

Last edited by vegetablevn; 2010-10-15 at 03:27 AM.
Reply With Quote
Reply

Bookmarks

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Forum Jump

Similar Threads
Thread Thread Starter Forum Replies Last Post
Braebury - Opinions? edy2008 Ottawa 15 2011-11-20 10:58 AM
Braebury Referral Program - Anyone buying Braebury ? edy2008 Ottawa 8 2008-07-06 03:15 PM
Braebury - fee for quote? ElectricMayhem Ottawa 8 2008-07-06 03:13 PM



All times are GMT -4. The time now is 09:34 AM.



Copyright © PHAND Corporation
This document may not be used elsewhere without the expressed written consent of PHAND Corporation.
*** There is no association between this website and any builder. ***

Powered by vBulletin® Version 3.8.10
Copyright ©2000 - 2019, vBulletin Solutions, Inc.