Default Phase 9 Findlay Creek - Tamarack

Has anyone who is in phase 9 been given a delay for their closing date in phase 9 I would like to share any experiences with others in my phase
Reply With Quote
  #2  
Old 2010-02-16, 09:08 PM
mc_ottawa's Avatar
mc_ottawa mc_ottawa is offline
Senior Member
Regular User
 
Join Date: Jul 2009
Location: Ontario, Ottawa
Posts: 1,209
Default

No delay for us yet... Then again, we aren't scheduled to close until December.

Did you get a delay notice?
__________________


Reply With Quote
  #3  
Old 2010-02-17, 12:03 AM
FindlayCreek FindlayCreek is offline
Member
Regular User
 
Join Date: Jan 2010
Location: ON/Ottawa
Posts: 48
Default

Quote:
Originally Posted by mc_ottawa View Post
No delay for us yet... Then again, we aren't scheduled to close until December.

Did you get a delay notice?
Our Closing is in June, so we await the dreaded delay letter sometime in March?
Reply With Quote
  #4  
Old 2010-02-17, 12:28 AM
mc_ottawa's Avatar
mc_ottawa mc_ottawa is offline
Senior Member
Regular User
 
Join Date: Jul 2009
Location: Ontario, Ottawa
Posts: 1,209
Default

From everything I've been told (by Tamarack at least), Phase 9 has been going on as scheduled and there hasn't been any major delays. The longest delay thus far in the last couple of phases has been two weeks, apparently?
__________________


Reply With Quote
  #5  
Old 2010-02-17, 02:08 PM
findlaycreek01's Avatar
findlaycreek01 findlaycreek01 is offline
Senior Member
Regular User
 
Join Date: Jul 2008
Location: Ottawa
Posts: 213
Default

We closed Nov 26 in phase 9. Our original date was Oct 26. They tried to delay a 2nd time by asking if we would accept another delay, but we said no and closed nov 26.
__________________
Findlay Creek (Phase 9)
Tamarack Bradbury
Closed: November 2009
Reply With Quote
  #6  
Old 2010-02-19, 11:28 AM
bruins bruins is offline
Member
Regular User
 
Join Date: Jan 2010
Location: Ontario
Posts: 97
Default

Quote:
Originally Posted by mc_ottawa View Post
From everything I've been told (by Tamarack at least), Phase 9 has been going on as scheduled and there hasn't been any major delays. The longest delay thus far in the last couple of phases has been two weeks, apparently?
I was told the same from Tamarack. We close October 19, 2010
Reply With Quote
  #7  
Old 2010-02-19, 12:29 PM
SuperSaiks SuperSaiks is offline
Member
Regular User
 
Join Date: Jan 2009
Posts: 86
Default

Hey bruins get to work
Reply With Quote
Reply

Bookmarks

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Forum Jump

Similar Threads
Thread Thread Starter Forum Replies Last Post
Tamarack manors in Jackson Trails/Findlay Creek/Chaperal Orleans canabiz Ottawa 11 2012-01-05 09:38 AM
Anyone in Phase 8 in Findlay Creek? Brian_JenMc Ottawa 730 2010-08-13 09:13 PM
When will the commercial phase begin in Findlay Creek? bruins Ottawa 6 2010-03-01 06:55 PM
phase 10 findlay creek - tamarack mc_ottawa Ottawa 3 2010-02-18 10:40 AM
Findlay Creek Phase 9 findlaycreek01 Ottawa 2 2009-03-27 08:55 PM



All times are GMT -4. The time now is 03:13 AM.



Copyright © PHAND Corporation
This document may not be used elsewhere without the expressed written consent of PHAND Corporation.
*** There is no association between this website and any builder. ***

Powered by vBulletin® Version 3.8.10
Copyright ©2000 - 2020, vBulletin Solutions, Inc.